25 workers were employed to finish a job in 12 days. Five workers, however, left after working only for 4 days. The rest of the job was completed by remaining 20 workers. In how many days was the total job work compited?
25 workers were employed to finish a job in 12 days. Five workers, however, left after working only for 4 days. The rest of the job was completed by remaining 20 workers. In how many days was the total job work compited?
.
Option A: 18
Option B: 14
Option C: 15
Option D: 16
Correct Answer
Option: b
Explanation
.